Progress at Topsham

86 Bed Care Home

Progress photos of the 84 bed care home at Topsham for our Client Lancer Scott delivering this project for  Cinnamon Care Collection  in conjunction with KWL Architects

Planning conditions for this project stipulated that the superstructure of the development needed to demonstrate a 19% reduction in CO2 emissions over that necessary to meet the requirements of the 2013 Building Regulations.

To achieve this a “Fabric First” approach was adopted switching from a traditional load bearing masonry structure to a hot rolled steel frame with heavily insulated external walls.

This structure-led solution also accelerated the build programme leading to a water tight structure much earlier that would have been possible otherwise.

 

 

 

Arc Engineers have been a valued structural engineering partner on a number of Cinnamon Luxury Care projects. We value their design skills and look forward to working with them on many projects in future.

The team at ARC Engineers are the perfect complement to our Professional Team to provide for all our Civil and Structural Engineering requirements.

We’ve worked with Arc Engineers for a number of years and on some varied and challenging projects and have always received a good quality service. Project delivery is always client focused with a focus on cost effective solutions to technical issues and ensuring project deadlines are always met.

'